Coming Soon: Construction On South Higuera Street

Construction for the Higuera Complete Streets Project is expected to begin as early as August 24, 2026.
Post Date:08/12/2026 4:00 PM

 SLO in Motion logo on the left and the phrase Headed in the Right Direction on the right

Return to SLO in Motion News


Starting late August 2026, improvements will begin on various sections of Higuera Street. These improvements are part of the Complete Streets initiative, the City’s efforts to enhance safety, accessibility and connectivity for all road users in San Luis Obispo. Through SLO in Motion, the Higuera Complete Streets project reflects our community’s commitment to well‑maintained streets, easier connections, and a transportation network that supports everyone, no matter how they get around.  

Key project highlights include: 

  • Improve pedestrian crossings and accessible curb ramps   
  • Strengthen connections to transit and nearby neighborhoods 
  • Increase visibility and separation for people bicycling 
  • Upgrade traffic signals to improve safety and reduce emergency response delays 
  • Repair potholes and rehabilitate pavement  

Complete Streets improvements are planned on:   

  • Higuera Street from Los Osos Valley Road to Marsh Street   
  • Madonna Road from Higuera Street to the US 101 Overpass  
  • Meadow Park Neighborhood (Bridge Street, Exposition Drive, Corrida Drive, and Woodbridge Street)

A map graphic showing the Higuera Complete Streets Project area that is planned to begin in the fall of 2026

Construction Timeline and What to Expect 

Work is anticipated to begin as early as Monday, August 24, 2026, where we expect to start work near the Los Osos Valley Road and S. Higuera intersection and make our way up north. Work will move throughout the project area in phases and is expected to be completed by spring 2027. Because of this, most roadway work in a particular location is expected to last a few weeks or less before crews move to the next area. During construction, access to sidewalks, driveways, and businesses will be maintained whenever possible. If temporary access disruptions are needed, businesses will be notified in advance, and alternate routes or adjusted work hours will be used to help minimize impacts.   

Standard construction hours will be Monday – Friday from 7 a.m. to 4 p.m. with the possibility of night work to minimize traffic impacts during the most disruptive phases of construction.  

During construction community members can expect:  

  • Temporary closures of traffic lanes, bike lanes, and sidewalks  
  • Lane shifting and reduced speeds through construction zones 
  • Temporary detours and traffic noise 
  • Odors during roadway paving/sealing, and striping work 
  • Use of heavy equipment 

Impacted residents and businesses will receive advance notice before work begins on their street. We appreciate the community’s patience as we work on these City improvements.   

SLO in Motion: Investing in a Connected & Safer Community 

These temporary construction projects go beyond repairing roads. They're a vital part of our ongoing collective vision for San Luis Obispo, one that seeks to create a more resilient, vibrant, inclusive, and forward-thinking community. 

“The Higuera Complete Streets Project is an important investment in safety, accessibility, and long‑term road maintenance for our community on one of our most important corridors,” said Transportation Manager, Luke Schwartz. “As work moves through each phase of construction, we are repairing roadway pavement, improving pedestrian crossings, and bicycle facilities, modernizing traffic signal equipment and investing in a foundation that allows people to travel more comfortably and reliably to work, school, and other destinations. Each part of this project brings us closer to a more connected, resilient, and inclusive San Luis Obispo.”


For more information about this project, please visit the Higuera Complete Streets Project webpage.

Media Contact: Jennifer Rice, Active Transportation Manager – Public Works & Utilities, jrice@slocity.org


 

Please keep an eye out for orange cones and active construction sites and remember to:  

watchface iconAllow Extra Travel Time: Due to ongoing construction, please allow for extra travel time when navigating these areas. 


Traffic cone iconSlow Down for Construction Crews: Please reduce your speed and exercise caution when driving through construction zones. Slow down if you see orange cones. Our dedicated crews are working diligently to make San Luis Obispo safer for everyone.

 


Why These Projects Matter

While these construction projects may create temporary disruptions, we want to emphasize their significance in shaping the future and protecting the City San Luis Obispo. Each project is community-driven and essential to our city's future. They are not just about fixing roads, creeks, and adding bike lanes; they're a vital part of our collective vision for San Luis Obispo. 

Once complete, they will keep SLO in motion, keeping our infrastructure in tip-top shape, making it easier and safer for community members to get around, connecting communities, and creating healthy recreational opportunities for community members.  

As you navigate through these construction zones, please remember that the inconveniences you may face today are investments in a brighter and more accessible tomorrow. 

Thank you for being part of this journey with us. Together, we are shaping the future of San Luis Obispo, one project at a time. 


 

Other Construction and Traffic Impacts  

Every week, we post current traffic updates and road closure information for all Public Works projects happening in San Luis Obispo. Follow these updates on our Construction and Traffic Updates webpage.  

Stay Involved

Website: Get to know the SLO in Motion projects by visiting www.slocity.org/sloinmotion
Email us: sloinmotion@slocity.org 
Call us: 805-783-7887 
Sign up for project e-notifications: www.slocity.org/subscribe

Return to full list >>